下列10kV三芯户内冷缩式电力电缆终端头制作流程正确的是()
A.电缆测试→剥切电缆外护套→剥切电缆铠装→剥切电缆内护套→焊接地线→剥铜屏蔽层→收缩三指套→剥半导体层→剥线芯绝缘层→安装终端→安装相色罩帽→压接接线端子→电气性能测试→填写记录 B.剥切电缆外护套→电缆测试→剥切电缆铠装→剥切电缆内护套→焊接地线→收缩三指套→剥铜屏蔽层→剥半导体层→剥线芯绝缘层→安装终端→安装相色罩帽→压接接线端子→电气性能测试→填写记录 C.电缆测试→剥切电缆外护套→剥切电缆铠装→剥切电缆内护套→焊接地线→收缩三指套→剥铜屏蔽层→剥半导体层→剥线芯绝缘层→安装终端→安装相色罩帽→压接接线端子→电气性能测试→填写记录 D.电缆测试→剥切电缆外护套→剥切电缆铠装→剥切电缆内护套→焊接地线→收缩三指套→剥铜屏蔽层→剥半导体层→剥线芯绝缘层→安装终端→压接接线端子→安装相色罩帽→电气性能测试→填写记录